Project Total Without Sports Fields: $116,395,875

Waukee Community School District Board of Education will be calling for a special election to be held on February 6, 2018, to contract indebtedness and issue General Obligation Bonds in an amount not to exceed $117,000,000 to provide funds to build, furnish and equip a new high school building and improve the site, including grading of access routes and the 160-acre site; and to improve, remodel, furnish and equip the current high school facility.

Building Construction: $77,815,000
  • 395,000 square feet
  • $197 per square foot
  • Greenhouse $360,000 Alternate
Site Development: $12,679,730
  • Grading, Control, Stabilization: $5,188,730
  • Paving, Utilities, Landscaping, Improvements: $7,491,000
Furniture & Equipment: $9,000,000
  • Furniture: $5,000,000
  • Technology: $2,000,000
  • Building Automation Systems: $2,000,000
Off-Site Street Improvements: $3,000,000
  • Road/Right-of-way Improvements (10th Street)
Existing High School Improvements: $1,098,500
  • Interior Renovations, Technology, ect: $1,000,000
  • Professional Fees: $98,500
Project Development Soft Costs: $12,442,645
  • Topographical Survey: City Cost
  • Soil Investigation: $36,700
  • Soil Investigation Staking: $5,000
  • Printing of Documents: $75,000
  • Construction of Special Testing: $285,000
  • Sanitary Sewer Fee: $445,000
  • Building Permit Fee: $176,000
  • Water/Sewer Connection Fees: $60,000
  • Life Cycle Cost Analysis: $25,000
  • Builder’s Risk Insurance: $75,000
  • Energy Code Inspections: $400,000
  • Professional Fees: $5,662,384
  • 5% Design/Construction Contingency: $5,197,662

 

Paid for with PPEL

Sports fields and improvement cost will be paid for using funds from the Physical Plant and Equipment Levy (PPEL).